Title Grid integration of generator plants – Low-voltage – Test requirements for generator units to be connected to and operated in parallel with low-voltage distribution networks
Acronym VDE V 0124-100
Published Year 2020
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Testing Procedure
Country DE
Link https://www.vde-verlag.de/standards/0100571/din-vde-v-0124-100-vde-v-0124-100-2020-06.html
Abstract
Title Automatic disconnection device between a generator and the public low-voltage grid; Amendment 1
Acronym VDE V 0126-1-1/A1
Published Year withdrawn
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic EMC, Power Quality
Country DE
Link
Abstract
Title Engineering Recommendation P2/7
Acronym Engineering Recommendation P2/7
Published Year P2/issue 7, 2019
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Protection/ Safety
Country GB
Link http://www.dcode.org.uk/assets/files/Qualifying%20Standards/ENA_EREC_P2_Issue%207_(2019).pdf
Abstract
Title Technical Regulation for Electricitygenerating Facilities of 11 kW or lower
Acronym
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Power Quality
Country
Link
Abstract
Title Electromagnetic compatibility (EMC) – Part 3-12: Limits – Limits for harmonic currents produced by equipment connected to public low-voltage systems with input current > 16 A and <= 75 A per phase
Acronym
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic EMC, Power Quality
Country
Link
Abstract
Title Requirements for the connection of micro-generators in parallel with public low-voltage distribution networks
Acronym EN 50438
Published Year Reviewed 2014
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic
Country EU
Link https://www.beuth.de/en/standard/oeve-oenorm-en-50438/215609466
Abstract
Title Royal Decree, on interconnection of photovoltaic installations to the low voltage grid. Resolución 31/5/01. 31/5/01 rule, defines the contract model and the invoice model for low voltage connected PV
Acronym R.D. 1663/2000
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source PV
Topic Electrical Installation
Country ES
Link
Abstract
Title DK5950
Acronym DK5950
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source PV
Topic Electrical Installation
Country IT
Link
Abstract
Title CONDITIONS TECHNIQUES DE RACCORDEMENT AU RÉSEAU PUBLIC DES INSTALLATIONS DE PRODUCTION AUTONOME DÉNERGIE ÉLECTRIQUE DE MOINS DE 1 MW
Acronym AN210797
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Protection/ Safety
Country FR
Link
Abstract
Title Technische Anschlußbedingungen für den Anschluß an das Niederspannungsnetz TAB 2007,
Acronym TAB Niederspannung 2007
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Electrical Installation
Country DE
Link
Abstract
Title Journal officiel Décret n° 2003-229 du 13 mars 2003 relatif aux prescriptions techniques générales de conception et de fonctionnement auxquelles doivent satisfaire les installations en vue de leur rac
Acronym NOR INDI0301060D
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Electrical Installation
Country FR
Link
Abstract
Title Arrêté du 17 mars 2003
Acronym
Published Year
Segment LV connected (> 5 kW /16 A per phase and < 1 kV)
Energy Source non-specific
Topic Metering, Power Quality
Country
Link
Abstract